FTM Indoor Positioning — Master Plan

Agents: start at docs/AGENT_BRIEF.md, then your phase document under docs/phases/. Each phase document opens with a Start here block giving its branch, worktree command, dependencies and definition of done — it is a complete work order.

This document is the index and the source of the project-wide constraints (§5). docs/HARDWARE_FINDINGS.md is normative measured fact.


1. Goal

Build a 3D indoor positioning system from ESP32-C3 boards using Wi-Fi FTM (Fine Timing Measurement).

  • One initiator (mobile node) measures its distance to several anchors (stationary FTM responders).
  • Distances plus known anchor positions give a 3D fix by trilateration.
  • Target accuracy is not demanding — the FTM hardware quantises to 15 cm and that is explicitly acceptable for this project. This is a feasibility bench, not a metrology instrument.
  • Currently available hardware: 2× ESP32-C3. Everything must be designed for N anchors and validated with 2. Never hardcode a two-board assumption.

2. Current state

Item Status
ESP-IDF v5.5.2 at C:\Users\murilo\esp\v5.5.2 Working
Board A — COM3, ESP32-C3 Working, used as responder
Board B — COM4, ESP32-C3 rev v0.4, MAC 14:63:93:8d:96:e4 Working, used as initiator
Espressif FTM console example Built, flashed, end-to-end FTM verified
Measured baseline at ~1.2 m separation mean 1.22 m, 28–30/30 valid readings
Bench fixture: boards fixed 1.00 m apart Standing setup — tests may assert 1 m ground truth
Git repository Initialised, branch main
Docker Desktop 4.82.0 + ftm-dev image Installed; firmware build, Ceedling, IDF linux target all verified
Python venv + test libs Installed and verified

All hardware facts are in docs/HARDWARE_FINDINGS.md. That document is normative — do not re-derive these numbers, and do not contradict them without new measurements.

3. Repository layout (target)

ftm_measurement/
├── docs/
│   ├── PLAN.md                   <- this file
│   ├── AGENT_BRIEF.md            <- agent onboarding; read before any phase
│   ├── HARDWARE_FINDINGS.md      <- verified measurements, normative
│   ├── ARCHITECTURE.md           <- layering, swappable modules, contracts
│   ├── RTOS.md                   <- tasks, queue, overflow policy
│   ├── TESTING.md                <- test framework + worst-case catalogue
│   ├── CONTAINER.md              <- container (build + host unit tests only)
│   ├── PROTOCOL.md               <- ftmbin wire format (one serialiser)
│   ├── WORKFLOW.md               <- git rules, merge gate, reports
│   └── phases/
│       ├── PHASE_0_test_infra.md
│       ├── PHASE_1_bench_firmware.md
│       ├── PHASE_2_calibrator.md
│       ├── PHASE_3_definitive_firmware.md
│       ├── PHASE_4_protocol.md
│       ├── PHASE_5_positioning.md
│       └── PHASE_6_e2e_and_manual.md
├── tools/
│   ├── bench_firmware/           <- Phase 1: board validation firmware
│   ├── bench/                    <- Phase 1: host validation scripts
│   └── calibrator/               <- Phase 2: firmware + tkinter UI
├── components/                   <- Phase 3: the definitive layered firmware
│   ├── domain/
│   ├── services/
│   └── drivers/
├── docker/                       <- Phase 0: build/test container
└── tests/                        <- all committed tests (WORKFLOW.md §4)

There is deliberately no ESP-IDF project at the repository root. Phase 1 moved the bench example into tools/bench_firmware/; the definitive firmware (Phase 3) lives in components/ with its own project. A root main/ would be ambiguous about which firmware it belongs to.

4. Phase overview

Phases are ordered by dependency. Each is independently assignable.

Phase Deliverable Depends on Doc
0 ✅ Container + test infrastructure — merged — PHASE_0
1 ✅ Bench validation firmware in tools/ — merged — PHASE_1
2 Calibration firmware + tkinter UI → CSV 1 PHASE_2
3 Definitive layered firmware 0, 2 PHASE_3
4 Binary protocol + .ftmlog logging + replay 3 PHASE_4
5 Positioning — host-first from logs, then target 3, 4 PHASE_5
6 E2E suite + human-in-loop movement test 3, 4, 5 PHASE_6

Phases 0 and 1 have no dependencies and may run in parallel.

Phase 4 exists so Phase 5 can be done offline. The protocol, .ftmlog capture and replay tooling let the 3D algorithm be developed and proven on the host against recorded real measurements — with their real noise and drift — before any of it is compiled for the target. Phase 5 is then split: 5a host, 5b target, one shared source file.

The container and all toolchains are installed and validated (docs/CONTAINER.md §8).

5. Non-negotiable constraints

These apply to every phase. An agent violating one should stop and flag it.

  1. Every feature has unit tests covering worst-case behaviour, not just the happy path. See the worst-case catalogue in docs/TESTING.md §4. A PR with only happy-path tests is incomplete.
  2. Every feature is exercised end-to-end on real hardware. Both boards are permanently connected on COM3 and COM4. E2E tests run autonomously.
  3. The layering in docs/ARCHITECTURE.md is mandatory, including layers that are currently empty (drivers/devices/). Empty layers exist for standardisation and get a README.md explaining why they are empty.
  4. Swappable modules follow one pattern — interface vtable, Kconfig-selected implementation, shared contract suite (docs/ARCHITECTURE.md §2). This covers role selection and serialisation. No #ifdef scattered through business logic.
  5. Serialisation is a swappable module, consuming domain snapshots and producing bytes. It must not include a driver or ESP-IDF header, must not allocate, and must not perform I/O. Every implementation passes the shared contract suite (docs/TESTING.md §4.8).
  6. The measurement task never blocks on transmission (docs/RTOS.md). On queue overflow the oldest entry is discarded so the freshest reading always survives — this is a navigation system, and stale data is worse than no data. Loss is made observable by a msg_seq gap plus a dropped_total counter, both diagnostic only: navigation uses current data and never waits for or reconstructs missing messages.
  7. Design for N anchors. Two boards is the current test fixture, not the architecture. With fewer than 4 usable anchors the system reports RANGE_ONLY — per-station distances — and never fabricates a 3D fix.
  8. Fix status travels with the data. Every cycle sends NAV-STATUS with fix_quality and num_anchors. Absence is information: no NAV-POSITION message means no position. Never emit a position message with placeholder or zeroed coordinates — zero is a valid coordinate (docs/PROTOCOL.md).
  9. Never hardcode calibration constants in logic. They come from the generated calibration table (Phase 2 output).
  10. Builds and host unit tests run in the container; flashing, E2E and manual tests run on Windows inside the project venv (docs/CONTAINER.md). Never pip install into the system or IDF Python. The container never touches the boards.
  11. Branch per feature; main is never committed to directly. Merges are human-approved after all tests pass and the results have been shown.
  12. Never weaken a pre-existing test to make your change pass. If you break a test you did not write, fix your implementation or stop and ask. This is the regression rule in docs/WORKFLOW.md §3 and it is absolute.
  13. Every branch ends with a work report at docs/reports/<branch>.md stating deviations and scope changes, and every commit carries the Co-Authored-By model trailer (docs/WORKFLOW.md §5–6).

6. Environment setup (every agent needs this)

Once Phase 0 is done, tools/dev.ps1 routes every command to the right place — container or host — and an agent should not need to think about which:

.\tools\dev.ps1 build            # container
.\tools\dev.ps1 test-host        # container: Ceedling + IDF linux target
.\tools\dev.ps1 coverage         # container: gcovr
.\tools\dev.ps1 flash responder  # Windows host
.\tools\dev.ps1 e2e              # Windows host, venv

Host ESP-IDF

The Windows host has ESP-IDF v5.5.2 at C:\Users\murilo\esp\v5.5.2, used for flashing and E2E.

export.ps1 fails from a plain PowerShell session because the Microsoft Store python alias shadows the IDF Python. Always prepend the IDF Python first:

$env:Path = "C:\Users\murilo\.espressif\tools\idf-python\3.11.2;" + $env:Path
& "C:\Users\murilo\esp\v5.5.2\esp-idf\export.ps1"

Shell state does not persist between tool calls — chain the export with the command, or use a wrapper script.

Console must be on USB-Serial-JTAG. These boards expose only the built-in USB-Serial-JTAG (VID 303A / PID 1001), not a UART bridge. Any firmware in this repo must set:

CONFIG_ESP_CONSOLE_USB_SERIAL_JTAG=y

Without it the REPL is unreachable and the failure is misleading: boot logs still appear on the COM port, but every write times out.

7. How agents should work these documents

  • Read your phase doc fully before starting. It lists preconditions, deliverables with exact paths, required tests, and acceptance criteria.
  • Do not expand scope. If a phase doc omits something you think is needed, record it in your work report (docs/WORKFLOW.md §6) rather than building it.
  • Record measurements, don't assume them. If you take a new hardware reading that contradicts docs/HARDWARE_FINDINGS.md, update that document and say so explicitly in your report.
  • Update the phase doc's status table when you finish.
  • Report honestly. If a test fails or a step was skipped, say so with the output. Do not describe unverified work as verified.